| Date: |
Description Of Work |
| June 1999 |
Removed Old Shelving beneath main windows |
| July - October 1999 |
Bilges drained, dried and treated with Hammerite. |
| Novemeber 1999 |
New breather pipes fitted to water tanks |
| December 1999 |
New inspection hatches fitted to Water tanks - "tanks are in excellent
condition!" - engineer's quote |
| January 2000 |
Reinforced floor timbers and screwed floor into place |
| February 2000 |
Removed Starboard main windows and refitted with new timber (Iroko)
and glass (8.8mm laminate). |